Leadership, Decisions, and Corporate Culture
A decision tree puts a value on a choice before the uncertainty is resolved and on the information that would resolve it. Experiments and field data show how judgement is tilted by overconfidence, anchoring, sunk costs, confirmation, and the planning fallacy, and how a cohesive group can decide worse than its best member. The unit then reads the measured evidence on leaders and bosses, defines corporate culture on Schein's three levels, shows how it is measured by employee surveys and what the measurements are associated with, and ends with what is known about changing it.
On the evening of 27 January 1986, thirty-four engineers and managers in Utah, Alabama, and Florida spent two hours on a telephone line deciding whether the Space Shuttle Challenger should be launched the next morning into the coldest weather any shuttle had ever flown in. The engineers of the company that built the booster rockets said no. Their managers, after a thirty-minute private discussion with the telephone line on mute, said yes. Nothing in the first nine units of this masterclass could have told the people on that line what to do, because the figures were not the problem. The problem was how a group of able people, under time pressure and with incomplete information, reaches a decision, and that is the subject of this unit. It asks how a decision under uncertainty should be made and how people actually make it, whether the person at the top of a firm matters as much as the business press assumes, and what the culture of a company is, how it can be measured, and why it is so hard to change. Motivation and teams were the subject of Unit 7 and structure the subject of Unit 9; boards, shareholders, and the pay of executives are questions of corporate governance and lie beyond this unit.
1 Decisions under uncertainty
Almost every decision a manager takes is taken before the facts are known. A product is launched before anyone knows whether customers want it, a plant is built before the demand it will serve exists, and a person is hired before anyone has seen them work. Unit 1 introduced the tool for such decisions, the expected value, which is the average of the possible outcomes weighted by their probabilities. If an outcome \(x_i\) occurs with probability \(p_i\), the expected value of the uncertain quantity \(X\) is \begin{equation} E[X] = \sum_i p_i\, x_i . \label{eq:ev} \end{equation} For example, a project that pays 60 million US dollars with probability 0.4 and loses 40 million with probability 0.6 has an expected value of \(0.4 \times 60 - 0.6 \times 40 = 0\). A manager who faces many such decisions and chooses the alternative with the highest expected value each time will, over the years, end up on average with more than a manager who chooses by any other rule, because the good and bad surprises average out. Where the outcomes are cash flows at different dates, the expected value is taken of their net present value, which Unit 6 defined, so that time and uncertainty are both accounted for.
Two cautions belong to this rule. The first is that a single decision which is large relative to the firm is not one of many, so the firm may reasonably prefer the alternative with the smaller spread of outcomes even at a lower expected value; the cost of capital of Unit 11 is one way to put a price on that preference, and Unit 11 also says what this simplification leaves out. The second caution is that the probabilities in Equation \eqref{eq:ev} are rarely known. They are estimates, and Section 2 is about what goes wrong when people make them.
1.1 The decision tree
A decision tree draws a sequence of choices and chance events from left to right. By convention a square marks a decision, where the manager chooses a branch, and a circle marks a chance event, where the world chooses a branch with the probability written on it. The payoffs stand at the right-hand ends. The tree is solved from right to left, which is called rolling back: at each circle the expected value of the branches is computed, and at each square the branch with the highest value is chosen and the others are crossed out. The value that remains at the root, the first square on the left, is the value of the whole decision before anything is known.
The most useful thing a tree shows is the value of waiting for information. Suppose the manager can run a market test before committing, which means a small launch in a few cities whose result says something, though not everything, about the national market. The test costs money and time, and a tree answers whether it is worth it. The worked case states the figures for one such decision.