Workers at the moving assembly line of Ford's Highland Park plant in 1913, assembling flywheel magnetos on a long bench with parts bins
Unit 04 · All masterclasses · 65 min

Operations, Quality, and Lean Production

Bottlenecks, queues, inventory, and how Toyota built quality into every step
Image: US National Archives, via Wikimedia Commons

How things get made and delivered, seen as a process with steps and times: the bottleneck that sets the capacity, Little's law that ties inventory to flow, and the queueing result that explains why a process that is 95 per cent busy makes customers wait far longer than one at 80 per cent. The unit then asks how much a shop should order at a time, measures inventory in days from the filings of Toyota and General Motors, and tells the story of the two ideas that changed how almost everything is made, the moving assembly line of 1913 and the Toyota Production System, before it ends with the control chart that tells a real change in a process from ordinary variation.

Preview: the beginning of the unit

A hospital’s emergency department registers a patient, assesses her, treats her, and sends her home or upstairs to a ward. A car plant turns about 30,000 parts into a car, and a bank turns a loan application into a decision. Seen from the operations manager’s desk these are the same thing, a process, and the same four questions apply to all of them. How much can the process do in an hour? Where does the work pile up? How long does a patient, a car, or an application spend inside? How is a defect caught before it reaches the customer? This unit answers the four questions with tools that fit on one page, and then tells the story of the two ideas, the moving assembly line of 1913 and the Toyota Production System, that changed how almost everything is made.

1 Processes, capacity, and the bottleneck

A process is a sequence of steps that turns inputs into an output that a customer wants. The thing that moves through the steps is called an item in this unit, whether it is a patient, a car body, a parcel, or a form. Every step has a processing time, the time one worker or one machine needs for one item, and the first thing an operations manager does with a new process is to draw it as a flow diagram with the measured processing time written into every box. Figure 1 shows such a diagram for the emergency department of Worked Case 1.

The capacity of a step is the largest number of items it can complete in a given time. A step with \(n\) identical workers or machines and a processing time \(t\) per item has the capacity \(n/t\). For example, one triage nurse who needs 6.5 minutes per patient can assess \(60/6.5 = 9.2\) patients an hour, and two such nurses can assess 18.5. The capacity of the whole process is the capacity of its slowest step, because no item can leave the process faster than it passes that step. The slowest step is the bottleneck, and the word is used exactly as for a bottle, where the narrow neck decides how fast the liquid pours, whatever the width of the body.

Two more quantities complete the vocabulary of this section, and both describe how the process is actually used rather than what it could do. The flow rate \(R\), which practitioners call the throughput, is the number of items that actually pass through the process per hour or per day. When customers arrive faster than the bottleneck can serve them, the flow rate equals the capacity and a queue builds; when they arrive more slowly, the flow rate equals the demand and part of the capacity stands idle. The utilization \(u\) of a step is the share of its capacity in use, and the flow time \(T\) is the time one item spends in the process from entry to exit, waiting included. One more word is needed for the pace of a process. The cycle time is the average interval between two items leaving the process, which is \(1/R\); a car line that completes 60 cars an hour has a cycle time of one minute.

The emergency department of Worked Case 1 drawn as a three-step process. The processing times are the measured averages of the department; the staffi…
Figure 1. The emergency department of Worked Case 1 drawn as a three-step process. The processing times are the measured averages of the department; the staffing is the assumption of the case. The physicians form the bottleneck, so the whole department can treat at most 6.3 patients an hour. Source of the times: Jones and Evans (2008), AMIA Annual Symposium Proceedings 2008, 338.